Chemical Storage Tank Installation – Northern Ohio
We installed a new chemical storage tank at a chemical plant in Northern Ohio and ran the new lines to put it into service, tying it into the plant’s existing process equipment.
Our scope included:
• Setting the new storage tank in its containment area.
• Welding a flanged outlet nozzle and installing a 3″ ball valve on the tank outlet.
• Fabricating and installing a steel support bracket for the outlet piping.
• Running carbon steel piping from the tank to the air-operated diaphragm transfer pump.
• Running a new overhead fill line along the ceiling on hangers, down to the top of the tank.
• Tying the new lines into the plant’s existing process equipment.

Tie-ins to existing equipment
The new lines tie into the plant’s existing process equipment. Tie-ins in a running chemical plant take careful planning around production and safety, and our crews handled them as part of the same job.

See more of our carbon steel and utility piping and equipment installation work.
Submit your request
For Inquiries, Give us a Call or Drop us an Email
latest projects
Chemical Storage Tank Installation – Northern Ohio
New chemical storage tank set, piped and tied into existing process equipment at a chemical plant in Northern Ohio.
Read more
Process Skids, Valve Matrices & UV Systems
Shop-built process skids, valve matrices and UV treatment systems, installed and piped into food and beverage plants.
Read more
Tank Staircases & Process Piping in Columbus, Ohio
Six stainless steel tank staircases plus sanitary process piping for a national beverage manufacturer in Columbus, Ohio.
Read more
Chiller Installation in Nashville, Tennessee
We installed a new Mueller chiller for a food processing plant in Nashville, Tennessee — crane set, sanitary stainless piping and tie-in to the production line.
Read more
Cheese Factory in Minnesota
We recently had the privilege of completing a pipe processing and installation project at a cheese factory in Minnesota.
Read more